In a process costing system that assumes that normal spoilage occurs at the end of a process, the costs attributable to normal spoilage should be assigned to

Sagot :

Answer:

Cost of goods manufactured (transferred out).

Explanation:

In a process costing system which assumes that normal spoilage occurs at the end of a process, the cost attributable to normal spoilage should be assigned to: (Cost of goods manufactured )