Sagot :
Answer:
If 4 men take 10 days, then it means 1 men will take 40 days. So from this you can calculate 5 people will take 8 days.
Or
We have a formula for this.
As you know, no of days will be in indirect proportion to no of men for a job, because if we increase count of men then days reduce.
So the formula will be
10/x=5/4
Where x is no of days by 5 men.
Hope this will be helpful to understand the concept of such type of questions. :)
Step-by-step explanation:
thc
[tex]{\overline{ \underline{ \huge {\boxed{\bold{ANSWER:}}}}}}[/tex]
4. If men can do a portion of job in 10 days, how many men can do the same job in 8 days
a. 5
b. 7
c. 6
d. 8
[tex] \huge \pink{EXPLANATION}[/tex]
4 men × 10 days ÷ 8 days
- 4 × 10 = 40
- 40 ÷ 8 = 5
Therefore 5 men can do the same job in 8 days
#CarryOnLearning
ᴀɴꜱᴡᴇʀᴇᴅ ʙʏ: ᴋɪᴢᴏᴏᴛʜᴇᴍᴏᴅ♤