The time (t) to complete a project varies inversely as the number( n ) of employees. If 7 people can complete a project in 10 days how long would it take 14 people to finish the same project?​

Sagot :

Answer:

5 days

Step-by-step explanation:

Inverse Proportion

7:10::14:n

n=5