which of the following is not true about installation ,testing, and commissioning?
a.quality air supply must be inspectec
b.performance deficiecy must be reveald.
c.performance data must not be copied
d.record of performance data can be a future reference.​


Sagot :

Answer:

Toggle navigation

Estates - Project Management

Coronavirus (COVID-19) updates: Safety information for academic year 2020-21

Latest information for current students and staff

HomeAdministration and support servicesEstates - Project ManagementProject proceduresProject processesDesign ManagementTesting and commissioning (Stage 6)

Testing and commissioning (Stage 6)

Project Process Map

Commissioning programme

The Main Contractor shall prepare a programme in the form of a GANTT chart that shows each element of the testing and commissioning process (including client validation and witnessing where specified) for all those services required under the contract and/or for compliance with statutory requirements.

The programme shall set out the proposed sequence, taking into account any linked activities. The programme shall address the requirements for testing, commissioning, validation and client witnessing of the controls as set out in the Building Engineering Services Particular Requirements‌ (pdf).

The programme shall be submitted to the Project Manager and Engineering Team Clerk of Works for review.

Explanation: