Sagot :
Answer:
B.
Step-by-step explanation:
6 workers do 3 storey house in 8 days
12 workers do 3 storey house in 4 days
6 × 2 = 12workers
kasi na doble yung mga trabahador kaya 4 na araw nalang para matapos ang gagawin
8 ÷ 2 = 4days