If 6 workers can finish painting a 3 - storey house in 8 days, how long will 12 workers do the same work?

A. 2 days
B. 4 days
C. 6 days
D. 3 days​


Sagot :

Answer:

B.

Step-by-step explanation:

6 workers do 3 storey house in 8 days

12 workers do 3 storey house in 4 days

6 × 2 = 12workers

kasi na doble yung mga trabahador kaya 4 na araw nalang para matapos ang gagawin

8 ÷ 2 = 4days